Barking 278, barking
Alfred’s Way, Barking
Link were appointed by Bridge Industrial to lead discussions with TfL and obtain S278 Technical Approval for the required improvements to an existing access onto the A13 Alfred’s Way, Barking.
The proposed detailed design was to be in accordance with Design Manual for Roads and Bridges and Transport for London design standards in line with the consented planning applications details, including:
- Full 2D and 3D design and setting out
- Pavement and Kerbing construction
- Road markings and signage to TSRG
- Stage 1/2 Road Safety Audit responses
The scope included detailed discussions with TfL and RMS to agree the final arrangement and construction requirements while considering site constraints, timescale risks and costs for our client. Ultimately, our input included detailed negotiations to support commuted sums calculations and the final S278 agreement between our client and TfL.
Bridge Industrial broke ground in September 2022 and has some interesting features being a Net Zero Carbon Development. You can read more about it below.
Team Member Contact
Chris Hadjivassiliou
Director
MEng (Hons) CEng MICE